CommercialSolarLondon Get a Quote

UK Power Networks G99 application for London commercial solar

Every commercial solar system in London connects to UK Power Networks' distribution network, and the G99 application is the one piece of paperwork that can move your whole programme. Here is how it works and how to keep it off the critical path.

Last verified: against the sources listed at the foot of this page.

Who UKPN are and why they decide your timeline

UK Power Networks operates the distribution network across London, the South East and the East of England — the cables, substations and transformers between the national grid and your meter. Connecting generation to that network requires their permission under the G99 engineering recommendation for anything above 16A per phase, which in practice means every commercial system. The installation itself takes weeks; UKPN's assessment can take months depending on size and network state. Projects that treat the application as an afterthought discover this the expensive way.

What UKPN assesses

The question is always the same: can the local network absorb your export without voltage or thermal problems? London's urban network is, on the whole, strong — dense, well-reinforced, built for heavy loads. Three answers come back. Clean approval: common for systems sized to building load in well-served areas. Approval with export limitation: increasingly standard for larger systems on busier feeders — you connect now, with a cap on export enforced by a control device. Reinforcement quotation: the rare-in-London case where full export requires network upgrades, priced to the applicant. For most London businesses the second outcome is commercially trivial, because city buildings consume the bulk of what they generate anyway.

The London sequencing play

A good sequence puts the G99 application immediately after desk feasibility, in parallel with the planning check and survey — not after the contract is signed. The application requires a stable single-line diagram and inverter schedule, both available once the preliminary design exists. Done this way, UKPN's response arrives while procurement and logistics planning proceed, and the installation slots in as approval lands. Done the other way, a signed contract waits two months for permission to connect — same project, slower cash flow.

Costs to expect

This guide does not quote UKPN application, witnessing or reinforcement fees. They are set in UKPN's own charging statement and change from year to year, so take the current figure from UKPN's published charges for your connection type and make sure the quote you are given shows it as a separate line. Export-limitation hardware, where a design needs it, is an installer price: ask for it itemised. The other cost lines are itemised on the London costs page.

Commissioning and witnessing

Larger systems may be witnessed at commissioning: UKPN attends (in person or by agreed evidence) while protection settings are proven — the relays that disconnect the system if the network fails — and any export limitation scheme is demonstrated working. Witnessing is routine when the design matched the application; it bites only when installers deviate mid-project, which is one more argument for the boring discipline of building what was applied for. After witnessing, the system is energised, registered and generating — and the only remaining UKPN interaction is the export meter doing its quiet work.

GRID FAQS

UKPN connection questions

What is the difference between G98 and G99?

G98 is the simplified notify-and-connect route for very small systems — up to 16A per phase, about 3.7kW single-phase or 11kW three-phase. Practically no commercial system qualifies. G99 is the application route for everything larger: UKPN assesses the network impact before granting permission to connect. Commercial solar in London means G99, applied for before installation, every time.

How long does UKPN take to approve a commercial solar connection?

G99 response times vary with system size and local network state: smaller applications on a healthy network can clear within weeks, while larger systems needing a network study take longer, occasionally many months where reinforcement options are being priced. Check current timescales with UKPN. This is why the application goes in as soon as the design stabilises — UKPN's clock, not the installation, sets most London project timelines.

What does export limitation mean for my returns?

An export limitation scheme caps what your system can push onto UKPN's network, enforced by a fast-acting control device. Your on-site consumption is untouched — and because power used on site avoids the retail unit price while exported power earns only the export rate, the loss from a cap is usually small next to reinforcement; ask for the modelled export loss in the proposal. It is almost always the right answer when the alternative is paying for reinforcement.

Do we need a new supply or substation for solar?

Rarely for rooftop-scale projects. Systems up to a few hundred kW normally integrate on the LV side of your existing supply. Sites with their own HV substation integrate behind it. The cases that get complicated — very large arrays on modest supplies — are exactly what the G99 study exists to resolve, and why no fixed price should precede UKPN's answer on a big system.

Which UK Power Networks area is my London building in?

Read the first two digits of the bottom line of your MPAN. 12 is London Power Networks, 10 is Eastern Power Networks and 19 is South Eastern Power Networks (all UK Power Networks); 20 is SSEN’s Southern network. Greater London is mostly the London area but the outer edge can be mixed, so check the MPAN rather than assuming from the borough.

Does UKPN G98 apply to a commercial solar system?

Only if the equipment is fully type-tested and the total connected at the premises is no more than 16A per phase (3.68kW single-phase, 11.04kW three-phase), counting any battery or hybrid inverter and earlier additions. Almost every commercial rooftop array is larger and needs a G99 application.

G98 or G99: the thresholds in numbers

G98 covers generation up to 16 A per phase — 3.68 kW. Anything above that connects under G99. The practical consequence: effectively every commercial rooftop array in London is a G99 job, because even a 4 kW inverter (17.4 A at 230 V) is already over the G98 line.

G98G99
ThresholdUp to 16 A / 3.68 kW per phaseAbove 16 A / 3.68 kW per phase
ProcessConnect first, notify UKPN within 28 daysApply first — no energisation before UKPN approval
Who it fitsDomestic and micro systemsEvery commercial rooftop array
Programme impactNoneOften the longest single item — start it before design freeze

Treat the G99 application as the programme’s critical path and sequence the prior approval determination alongside it — the two clocks run concurrently when they are started together.

UKPN G98: the notification route, and the 16 A line

G98 is the Energy Networks Association engineering recommendation for fully type-tested micro-generation. It covers equipment up to and including 16 A per phase of inverter AC output — about 3.68 kW on a single phase and 11.04 kW across three — which is why searches for “UKPN G98” mostly come from domestic and very small installs. The installer notifies the network operator after commissioning rather than applying for permission first; the period usually quoted is 28 days, but confirm the current rule on UKPN’s connections pages before relying on it. The equipment must be on the ENA type-test register.

Two things catch commercial buyers out. First, the 16 A limit applies to the total generation connected at the premises, so a hybrid or battery inverter, or more panels added to an existing G98 system, can take the total over the line and turn the job into a G99 application. Second, G98 is a notification, not an approval: nothing in it tells you the local network can absorb your export. For a commercial rooftop array the answer is almost always G99 — see the thresholds table above.

Which network operator serves your building?

Do not guess from the borough. Your electricity supply number (MPAN) carries the answer: the first two digits of the bottom line are the distributor ID, and they identify the network area your supply sits in.

MPAN distributor IDNetwork areaOperator
12LondonLondon Power Networks (UK Power Networks)
10Eastern EnglandEastern Power Networks (UK Power Networks)
19South Eastern EnglandSouth Eastern Power Networks (UK Power Networks)
20Southern EnglandScottish & Southern Electricity Networks

Greater London is mostly the London area, but the outer edge can be mixed, and parts of the Thames Valley fringe to the west are served by SSEN’s Southern network rather than UKPN, so the same G99 application can go to a different company. Read the MPAN first; it decides where the application is sent and whose headroom study you are waiting on.

Sources and last verified

Checked on . Secondary sources are labelled as such.

  • G98 and G99 scope. Energy Networks Association, Engineering Recommendations G98 and G99: G98 for fully type-tested micro-generation up to and including 16 A per phase, G99 for larger generation. Read the current issue number and amendments on the ENA site.
  • Network area by MPAN. The distributor ID is the first two digits of the MPAN bottom line, as described on the MPAN reference page and in EDF Energy’s distribution network operator guide. Confirm with your supplier or the industry MPAS service if the answer matters to a contract.
  • Response times. Network operators’ response times to connection applications are governed by Ofgem’s guaranteed standards of performance (see S.I. 2015/698, as amended, for metered connections; generation connections are covered by an Ofgem direction under the distribution licence). This guide does not quote a response time it could not verify: ask UKPN for the current timescale for your application type.
  • UK Power Networks. The application route, fees and portal are on UKPN’s own connections pages. No fee is quoted here: read the current schedule on UKPN’s pages.

Not confirmed here: UKPN’s published G99 timescales and fee schedule, and the effect of Ofgem’s Distribution Code modification DCRP/MP/24/01 on G98 and G99. Treat any timescale you read elsewhere, including on installer sites, as indicative until UKPN confirms it for your application.

Request a commercial solar quote for your building

Tell us where the building is and what it does. We reply by email. No obligation.